Auditor general maintains RADA breached procurement rules

usscmc by usscmc
January 16, 2020
Auditor general maintains RADA breached procurement rules
Share on FacebookShare on Twitter

AUDITOR General Pamela Monroe Ellis is standing by findings of a performance management audit of the Rural Agricultural Development Authority (RADA) that the agency breached procurement guidelines, based on investigations carried out by her office, on its management of the Farm Road Rehabilitation Programme (FRRP) from 2014 to 2019.

According to the findings of the report, which was tabled in Parliament in October, the authority’s process of selecting contractors was not always transparent or competitive.

The auditors said that of the 112 road rehabilitation contracts valued at $1.6 billion that were reviewed, RADA used the local competitive bidding methodology for only four contracts, valued at $90.8 million.

“Conversely, RADA utilised the limited tender methodology for 75 contracts valuing $1.04 billion,” the report said.

Monroe Ellis said RADA was unable to indicate the basis on which contractors were preselected for an invitation to bid on road rehabilitation contracts. Furthermore, she outlined that in six instances RADA used the limited tender methodology to award contracts, valuing $129.8 million, despite the procurement guidelines not being met, “thereby denying other qualified contractors the opportunity to participate in the procurement process”.

At yesterday’s meeting of the Public Accounts Committee (PAC) at Gordon House, chief executive officer of RADA Peter Thompson explained that the contracts were put to tender at one value but the responses returned at higher values, from which the lowest bidders were selected.

Government member and St Catherine South Western Member of Parliament Everald Warmington argued that this was normal par for the course in works contracting.

But the auditor general said: “I have not been advised of the estimation provided by Mr Thompson here this morning [but] the finding, as it is remains, there was a breach – unless Mr Thompson can provide evidence to the contrary.”

“I know that the heads of agencies oftentimes can provide an explanation which may appear reasonable, but it is my responsibility to point out where there are breaches, and even where I may think it’s reasonable, I cannot take it on myself to accept it because then I become complicit, and I will be called on to provide an explanation alongside the perpetrators of the act,“ added Monroe Ellis.

The probe also found that RADA utilised the direct procurement and emergency methodologies for 33 contracts, valuing $520.93 million, although the allowable circumstances permitting the direct and emergency procurement methodologies were not met.

Tender evaluation reports for the 112 contracts examined revealed no evidence that RADA assessed bidders to determine whether they met the minimum qualifying criteria in compliance with the Instruction to Bidders and Procurement Guidelines, the audit report said.

“We noted that RADA’s due diligence process related to the selection of contractors was limited to the validity of the Tax Compliance Certificate and the National Contracts Commission, and selection was based on the lowest bid. RADA did not provide any evidence it conducted a pre-qualification exercise of potential bidders for limited tender contracts,” the report stated.

Among the reasons cited by RADA were the budgetary allocation for the farm road rehabilitation programme before the end of the financial year, and the impact of land slippage and deterioration of the road surface due to continuous rainfall. The agency also said the selected contractor was already mobilised and engaged on similar projects in the parish or neighbouring parishes, and that the contractors possessed the necessary expertise and capability to perform the works satisfactorily and within budget.

Now you can read the Jamaica Observer ePaper anytime, anywhere. The Jamaica Observer ePaper is available to you at home or at work, and is the same edition as the printed copy available at

usscmc

usscmc

No Result
View All Result

Recent Posts

  • How Hapag Lloyd captured a major market share in the Container Shipping Industry in USA
  • Why USA’s East Coast is the Favorite Destination for Manufacturing Companies
  • How Trade Relations Between the USA and UK Improved After Keir Starmer Became Prime Minister
  • Tips and Tricks for Procurement Managers to Handle Their Supplier Woes
  • The Crazy Supply Chain of Walmart Spanning Across the Globe

Recent Comments

  • Top 5 Supply Chain Certifications that are in high demand | Top 5 Certifications on Top 5 Globally Recognized Supply Chain Certifications
  • 3 Best Procurement Certifications that are most valuable | Procurement Newz on Top 5 Globally Recognized Supply Chain Certifications

Archives

  • July 2024
  • June 2024
  • May 2024
  • April 2024
  • March 2024
  • February 2024
  • January 2024
  • December 2023
  • November 2023
  • October 2023
  • September 2023
  • August 2023
  • July 2023
  • June 2023
  • May 2023
  • April 2023
  • March 2023
  • February 2023
  • January 2023
  • December 2022
  • November 2022
  • October 2022
  • September 2022
  • August 2022
  • July 2022
  • June 2022
  • May 2022
  • April 2022
  • March 2022
  • February 2022
  • January 2022
  • December 2021
  • November 2021
  • October 2021
  • September 2021
  • August 2021
  • July 2021
  • June 2021
  • May 2021
  • April 2021
  • March 2021
  • February 2021
  • January 2021
  • December 2020
  • November 2020
  • October 2020
  • September 2020
  • August 2020
  • July 2020
  • June 2020
  • May 2020
  • April 2020
  • March 2020
  • February 2020
  • January 2020
  • December 2019
  • November 2019
  • September 2019

Categories

  • Global News
  • Supply Chain Updates

Meta

  • Log in
  • Entries feed
  • Comments feed
  • WordPress.org
  • Antispam
  • Contact Us
  • Disclaimer
  • Home
  • Privacy Policy
  • Terms of Use

© 2025 www.usscmc.com

This website uses cookies to improve your experience. We'll assume you're ok with this, but you can opt-out if you wish. Cookie settingsACCEPT
Privacy & Cookies Policy

Privacy Overview

This website uses cookies to improve your experience while you navigate through the website. Out of these cookies, the cookies that are categorized as necessary are stored on your browser as they are essential for the working of basic functionalities of the website. We also use third-party cookies that help us analyze and understand how you use this website. These cookies will be stored in your browser only with your consent. You also have the option to opt-out of these cookies. But opting out of some of these cookies may have an effect on your browsing experience.
Necessary
Always Enabled
Necessary cookies are absolutely essential for the website to function properly. This category only includes cookies that ensures basic functionalities and security features of the website. These cookies do not store any personal information.
Non-necessary
Any cookies that may not be particularly necessary for the website to function and is used specifically to collect user personal data via analytics, ads, other embedded contents are termed as non-necessary cookies. It is mandatory to procure user consent prior to running these cookies on your website.
SAVE & ACCEPT
No Result
View All Result
  • Home
  • Supply Chain Updates
  • Global News
  • Contact Us

© 2025 www.usscmc.com