How best to balance value and risk in procurement | Comment

usscmc by usscmc
January 23, 2020
How best to balance value and risk in procurement | Comment
Share on FacebookShare on Twitter

Iain-Parker-BW-2019

As an industry, we talk a lot about value and risk, but not always in the context of procurement. The way a construction project is set up and the manner in which it is bought are undeniably critical to its success.

The general objectives of the procurement process are to select a competent and committed full project team; to introduce each team member at the appropriate time; to secure value for money (the optimum balance between the highest standards of materials and workmanship, the shortest possible programme and the lowest possible cost) and to create incentives for the achievement of the client’s declared objectives.

How does a client best navigate this complex web of choices?

However, above all of this, value and risk are the principal focus of procurement arrangements – how value is secured and risk is disposed of. If there is a general rule, it is that the client should carry risk for no longer than they can create value by doing so. This value might be secured by getting a better building (however that may be defined) or by avoiding paying too much to offload the risk (as risk is not shed free of charge). 

It is no exaggeration to say that selecting the wrong procurement strategy can affect the final cost and programme outcome by a premium of some 10% – so how does a client best navigate this complex web of choices?

The choice of procurement arrangement will generally depend upon the risk profile of the client and the needs of the project. Risk is perceived as relating to cost and programme, and maximum risk transfer in these respects, from client to contractor, resides in the design and build option, which continues to be one of the most common routes.

There is also, though, a quality and fitness-for-purpose risk – one that impacts more heavily on users. For risk transfer to be effective, the means of governing it have to pass as well, and this means the control of design development will pass to the contractor once it has been appointed under a design and build arrangement to deliver the project.

The point at which this occurs, and the quality of project definition upon which the contract is based, are therefore critical; and it follows that quality and fitness-for-purpose risk tend to run in the opposite direction to cost-and-time risk – with a design and build option representing maximum risk to the client.

The critical nature of a completion date may not always allow time to follow the logical sequence of definition

Revisiting these issues therefore involves looking at the client’s priorities in respect of time, cost and quality and the point at which this trinity is balanced in a perception of value and the client’s attitude to risk (which may well be influenced by experience, possibly to the point of immovable prejudice, and by their decision-making structures). It would also consider the characteristics of the project (complexity versus simplicity, whether it is capable of full predefinition, the anticipated incidence of change, etc), the availability of project management, design and construction skills – generally and in the client organisation and, finally, the state of the market. 

All this also needs to be considered within the context of the programme – as the critical nature of a completion date may not always allow time to follow the logical sequence of definition, design, procurement and construction (for the whole of the project) in a way that would otherwise best protect the client against risk. These are complex issues that are often not debated for enough time, or by the right people, those who are critical to ensuring a successful strategy is implemented. The final important consideration is how to introduce the principles of partnering into the process, in the conviction that parties working together are more likely to produce the desired outcome than those in confrontation or conflict.

The keys to a successful partnering arrangement are creating an integrated team with clearly understood, shared objectives; the maximum opportunity for all involved to make a productive contribution to the development process; fair and equitable sharing of risk and reward; commitment to continuous improvement and the measurement of performance; means of resolving disputes or potential disputes that are as quick and constructive as possible and, finally, a desire to spread these principles as far as possible up and down the supply chain.

Iain Parker is a founding partner of Alinea Consulting 

usscmc

usscmc

No Result
View All Result

Recent Posts

  • How Hapag Lloyd captured a major market share in the Container Shipping Industry in USA
  • Why USA’s East Coast is the Favorite Destination for Manufacturing Companies
  • How Trade Relations Between the USA and UK Improved After Keir Starmer Became Prime Minister
  • Tips and Tricks for Procurement Managers to Handle Their Supplier Woes
  • The Crazy Supply Chain of Walmart Spanning Across the Globe

Recent Comments

  • Top 5 Supply Chain Certifications that are in high demand | Top 5 Certifications on Top 5 Globally Recognized Supply Chain Certifications
  • 3 Best Procurement Certifications that are most valuable | Procurement Newz on Top 5 Globally Recognized Supply Chain Certifications

Archives

  • July 2024
  • June 2024
  • May 2024
  • April 2024
  • March 2024
  • February 2024
  • January 2024
  • December 2023
  • November 2023
  • October 2023
  • September 2023
  • August 2023
  • July 2023
  • June 2023
  • May 2023
  • April 2023
  • March 2023
  • February 2023
  • January 2023
  • December 2022
  • November 2022
  • October 2022
  • September 2022
  • August 2022
  • July 2022
  • June 2022
  • May 2022
  • April 2022
  • March 2022
  • February 2022
  • January 2022
  • December 2021
  • November 2021
  • October 2021
  • September 2021
  • August 2021
  • July 2021
  • June 2021
  • May 2021
  • April 2021
  • March 2021
  • February 2021
  • January 2021
  • December 2020
  • November 2020
  • October 2020
  • September 2020
  • August 2020
  • July 2020
  • June 2020
  • May 2020
  • April 2020
  • March 2020
  • February 2020
  • January 2020
  • December 2019
  • November 2019
  • September 2019

Categories

  • Global News
  • Supply Chain Updates

Meta

  • Log in
  • Entries feed
  • Comments feed
  • WordPress.org
  • Antispam
  • Contact Us
  • Disclaimer
  • Home
  • Privacy Policy
  • Terms of Use

© 2025 www.usscmc.com

This website uses cookies to improve your experience. We'll assume you're ok with this, but you can opt-out if you wish. Cookie settingsACCEPT
Privacy & Cookies Policy

Privacy Overview

This website uses cookies to improve your experience while you navigate through the website. Out of these cookies, the cookies that are categorized as necessary are stored on your browser as they are essential for the working of basic functionalities of the website. We also use third-party cookies that help us analyze and understand how you use this website. These cookies will be stored in your browser only with your consent. You also have the option to opt-out of these cookies. But opting out of some of these cookies may have an effect on your browsing experience.
Necessary
Always Enabled
Necessary cookies are absolutely essential for the website to function properly. This category only includes cookies that ensures basic functionalities and security features of the website. These cookies do not store any personal information.
Non-necessary
Any cookies that may not be particularly necessary for the website to function and is used specifically to collect user personal data via analytics, ads, other embedded contents are termed as non-necessary cookies. It is mandatory to procure user consent prior to running these cookies on your website.
SAVE & ACCEPT
No Result
View All Result
  • Home
  • Supply Chain Updates
  • Global News
  • Contact Us

© 2025 www.usscmc.com