Overpriced bids submitted to Rail Baltic design procurement | News

usscmc by usscmc
July 7, 2021
Overpriced bids submitted to Rail Baltic design procurement | News
Share on FacebookShare on Twitter

Rail Baltic’s biggest challenge is at present completing the design of the main railway corridor and subsequently acquiring the relevant properties. All objects are currently being designed, the first of them has been completed and procurements for the remaining 14 objects – seven viaducts and seven ecoducts – are underway, Minister of Economic Affairs and Infrastructure Taavi Aas (Center) said at an extraordinary video sitting of the economic affairs committee of the parliament convened for discussing a mid-term report on Rail Baltic.

The main designs for the Pärnu and Ülemiste passenger terminals should be completed this summer. Completing the design of the main railway corridor is the priority, followed by the acquisition of lands, according to Aas. Construction procurements have proceeded according to plan and the state has received better prices than expected. While savings have been achieved in construction procurements, the state has had less luck with design procurements.

“We recently carried out procurement for the design of local train stops and did not receive any reasonable bids, they were all very overpriced,” Grünberg said.

Receiving reasonable design tenders has also been difficult previously.

“All we can do is announce a repeat procurement and hope it’ll provide better results,” Grünberg said.

Rail Baltic’s designs need to be completed within the next few years, together with the drawing up of designs for local stops and detailed plans. The latter two stages are planned to be carried out separately.

Until designs remain unfinished, lands cannot be acquired. Grünberg said that the acquisition of lands is underway in locations where the establishment of the rail corridor is certain and will not be subject to any more changes.

The acquisition of around one-third of lands under the rail corridor has been set in motion. Most of them are privately owned properties while some are in municipal and some in public ownership. 165 private properties have been acquired thus far.

Grünberg said that the land acquisition process has proceeded reasonably thus far and only in a limited number of cases have the properties been expropriated. The construction of the main corridor is planned to start next year.

Chairman of the economic affairs committee of the parliament Kristen Michal (Reform) said that it is important that the implementation of Rail Baltic in Estonia should stick to the agreed time frame that takes into consideration the financing agreement signed as a result of the Connecting Europe Facility’s (CEF) application round of 2014 and the amendments to the timetable approved in late 2019.

Altogether five CEF financing agreements have been signed in the three Baltic states, in addition to support from the European recovery fund, Rail Baltic coordinator Kristjan Kaunissaare said. Financing from the Structural Funds is planned to be used for the Parnu passenger terminal.

Grünberg said that the situation of the project is at present very good; however, the said funds will not be sufficient for carrying out the entire project, thus funding needs to be sought also from the next budget period.

Ahti Kuningas, deputy secretary general for transport at the Ministry of Economic Affairs and Communications, said that the ministry does not yet know the total cost of the project as the prices of materials are unpredictable. Estonia needs an estimated €200 million, Latvia €500 million and Lithuania even more on top of the funding that has already been made available.

“It all depends on how we proceed with the design and construction works as funding is redistributed at the end of each budget period,” Kuningas said. “Those who make more progress, get more money and those who don’t will lose theirs. We don’t know how much money will be redistributed, but we presume that the sum should cover our needs,” he added.

The first train ride should take place on the Rail Baltic corridor in five years. It is too soon to say, however, whether or not this will be a domestic route only and which railway companies will operate it. The European Commission expects for the entire project to be completed by 2030.

—

Follow ERR News on Facebook and Twitter and never miss an update!

usscmc

usscmc

No Result
View All Result

Recent Posts

  • How Hapag Lloyd captured a major market share in the Container Shipping Industry in USA
  • Why USA’s East Coast is the Favorite Destination for Manufacturing Companies
  • How Trade Relations Between the USA and UK Improved After Keir Starmer Became Prime Minister
  • Tips and Tricks for Procurement Managers to Handle Their Supplier Woes
  • The Crazy Supply Chain of Walmart Spanning Across the Globe

Recent Comments

  • Top 5 Supply Chain Certifications that are in high demand | Top 5 Certifications on Top 5 Globally Recognized Supply Chain Certifications
  • 3 Best Procurement Certifications that are most valuable | Procurement Newz on Top 5 Globally Recognized Supply Chain Certifications

Archives

  • July 2024
  • June 2024
  • May 2024
  • April 2024
  • March 2024
  • February 2024
  • January 2024
  • December 2023
  • November 2023
  • October 2023
  • September 2023
  • August 2023
  • July 2023
  • June 2023
  • May 2023
  • April 2023
  • March 2023
  • February 2023
  • January 2023
  • December 2022
  • November 2022
  • October 2022
  • September 2022
  • August 2022
  • July 2022
  • June 2022
  • May 2022
  • April 2022
  • March 2022
  • February 2022
  • January 2022
  • December 2021
  • November 2021
  • October 2021
  • September 2021
  • August 2021
  • July 2021
  • June 2021
  • May 2021
  • April 2021
  • March 2021
  • February 2021
  • January 2021
  • December 2020
  • November 2020
  • October 2020
  • September 2020
  • August 2020
  • July 2020
  • June 2020
  • May 2020
  • April 2020
  • March 2020
  • February 2020
  • January 2020
  • December 2019
  • November 2019
  • September 2019

Categories

  • Global News
  • Supply Chain Updates

Meta

  • Log in
  • Entries feed
  • Comments feed
  • WordPress.org
  • Antispam
  • Contact Us
  • Disclaimer
  • Home
  • Privacy Policy
  • Terms of Use

© 2024 www.usscmc.com

This website uses cookies to improve your experience. We'll assume you're ok with this, but you can opt-out if you wish. Cookie settingsACCEPT
Privacy & Cookies Policy

Privacy Overview

This website uses cookies to improve your experience while you navigate through the website. Out of these cookies, the cookies that are categorized as necessary are stored on your browser as they are essential for the working of basic functionalities of the website. We also use third-party cookies that help us analyze and understand how you use this website. These cookies will be stored in your browser only with your consent. You also have the option to opt-out of these cookies. But opting out of some of these cookies may have an effect on your browsing experience.
Necessary
Always Enabled
Necessary cookies are absolutely essential for the website to function properly. This category only includes cookies that ensures basic functionalities and security features of the website. These cookies do not store any personal information.
Non-necessary
Any cookies that may not be particularly necessary for the website to function and is used specifically to collect user personal data via analytics, ads, other embedded contents are termed as non-necessary cookies. It is mandatory to procure user consent prior to running these cookies on your website.
SAVE & ACCEPT
No Result
View All Result
  • Home
  • Supply Chain Updates
  • Global News
  • Contact Us

© 2024 www.usscmc.com